Home News Parking garage beneath Chestnut Street condo tower reopens after repairs

Parking garage beneath Chestnut Street condo tower reopens after repairs

by admin
0 comment

468 garages with an owners’association separate from the condominium owners’ association upstairs, Closed on July 9, 2021. It was about two weeks after the horrific collapse of a 12-story condominium in Surfside, Florida. Residents of the condominium were afraid of similar incidents When they learned that the garage board had not yet completed the concrete repairs that the engineering company considered urgent in 2018.

Mike Boucher, one of the five members of the garage’s owner’s board, said the repair would cost about $ 4 million.

Get 4 Weeks of Crain for $ 1

“It’s like a brand new garage,” Boucher said. The repair “should have been done many years ago,” he said.

According to Boucher, the delay was “no one wants to spend money.” But the risk of collapse was “never a real risk,” Boucher said.

In 2018, an engineering consultant reported to the garage owner that repairing concrete stanchions “must be done as soon as possible because it poses an imminent risk to the users of the facility and the structure itself.”

Walker consultant, a consulting firm, sent a letter to the garage owner in early July 2021, and as far as he knows, repairs “have never been done” and “probably worsened concerns. “.

With the disturbing image of surfside in mind, 111 E. Chestnut residents told Crane in July that “my stomach was agitated” and “I couldn’t sleep at night.” One resident said she had banned her family and other visitors from parking in the garage for the past few years because she learned of the repairs left behind.

On July 9, the Construction Department ordered the garage to be closed until repairs were completed.

Mr. Boucher paid about $ 7,200 to rent two spaces in the Chicago Avenue building during the 10-month closure, but his real concern is “have public space and run all the time. The man who couldn’t do it. ” How much did that man lose? “

Public parking occupies most of the space for 468 cars in the garage.

Garage manager Debra Bolden introduced a question to Don Barnes, regional manager for parking operator SP Plus. Burns did not immediately respond to the request for comment.

Last year, the initial estimate for repairs was $ 12 million, but eventually Garage Board found an engineering company (Wiss, Janney, Elstner Associates, or WJE) to work for $ 4 million. I did. Despite cutting costs by two-thirds, Boucher said the work was done on the same basis. “When working in the city of Chicago, there is no easy way,” said Boucher. “They had an inspector here every week.”

On May 26, the City Construction Bureau lifted the closure order, and spokesman Michael Puccinelli confirmed Crain’s. According to a statement from the agency, the inspection “confirmed that the necessary structural repair work had been completed.”